Battery Storage in Germany: A Grid Operator’s View - 50Hertz
Podcast: Transmission · Ysabelle Swan
Opublikowano: 2026-10-20
Battery storage in Germany has a grid connection problem: far more projects want to connect than the grid can take, so Germany has scrapped first come, first served and moved to a maturity-based allocation scheme that rewards projects that are ready to build. But for 50Hertz and Germany's other transmission system operators, connecting BESS is only half the challenge. Merchant batteries could push grid congestion costs and grid fees up, or bring them down.Wilhelm Kiewitt, Head of Energy Economics at 50Hertz, one of Germany's four transmission system operators, joins Ed Porter to explain how a grid operator sees the...